The "User assignment" can be set up as follows:
In the event of modification of the person responsible for an entity, the use of formulas makes it possible to maintain the signing circuits as they are implemented, without having to modify anything, since this modification is automatically taken into account when the entity is modified.
This screen is comprised of two parts: The first part is used to enter the company or site code of review requests definition, the second part is used to view a grid displaying all the objects containing a review request.
The maximum number of lines authorized by selection is 500.
Each review request can be initialized individually by carrying out a selection in the column "Processing" or globally via the button "Review all" or "Reject all".
Presentation
The grid displays the review requests to be approved by the signer.
For review requests with status "Multiple", the amounts are not displayed. With a right click, it is possible to access the button Review detail listing the review requests carried out for each review level: Envelope, budgets, lines.
Close
Fields
The following fields are present on this tab :
Selection
| Field entered via the next signatory code of the approval circuit of revisions. |
| Site or company code, to be entered or selected from the list. This code makes it possible to select all review requests to be signed by the User for this Company. If the information entered corresponds to a company, the selection displays all the objects defined for the company, including those defined for the sites of this company. If the information entered corresponds to a site, the selection only displays the budget objects defined for this site. |
| Title associated with the site or company code. |
Review
| The button "Review all" is used to select, in a single operation, all the budget objects originating from the selection for refusal of the review request. Using it replaces, in the column "Processing", the status "None" with the status "Review". This action can be cancelled by using the same button that recovers the selection in status "None". |
| The button "Reject all" is used to select, in a single operation, all the budget objects originating from the selection for refusal. Using it replaces, in the column "Processing", the status "None" with the status "Reject". This action can be cancelled by using the same button that recovers the selection in status "None". |
Refusal
Grid Details
| This columns proposes three options: None (Default status of the selected budget objects), Review and Refuse. Each review request can be approved or refused by selecting the appropriate processing in an individual way. For a global processing of all the review requests, use the button "Review all" or "Reject all". |
| Code of the review request reason entered or selected in the miscellaneous table 349. |
| Text field used to enter a detailed revision reason. |
| Level description of the object submitted for approval: Envelope, budget fiscal year and budget line. The level "Multiple" indicates that the revision concerns several objects: envelope, budgets and/or lines. In this case, the amounts are not displayed. With a right click on the line, it is possible to access the button [Revision detail] listing the revision requests carried out for each revision level. |
| Code of the budget envelopes relating to a revision request, submitted for approval. |
| Description associated with the budget envelope code. |
| Accounting fiscal year code associated with budgets by fiscal year. |
| Budget account entered for a budget line. |
| Code of the currency used to manage envelopes, budgets and budget lines, controlled in the currency table. |
| Budgeted amount before revision, expressed ex tax, of the selected envelopes, budgets and budget lines. This amount corresponds to the approved amount, increased or decreased, of previous revisions. |
| Amount of the requested revision, expressed ex tax. This information is only displayed for an approval by object or by access to the detail of a multiple approval. |
| Amount, expressed ex tax, entered in the revision request, to be taken from the reserve:
|
| Amount expressed ex tax entered in the revision request, to be taken from the Left to distribute:
|
| Amount, expressed ex tax, entered in the revision request, corresponding to the requested envelope increase. |
| Total of the purchases requests, orders, posted invoices on the budget lines, budgets and envelopes. This information is displayed only for an approval by object or via the detail of a multiple approval. |
| Balance of the budget lines, budgets and envelopes corresponding to the budgeted amount - the actual amount. This information is displayed for a "single" revision. For this "multiple" revision, this zone is not loaded, you have to check the table "Detail". |
| If the envelope is attached to a project, its code will be displayed in this column. |
| Entity responsible for the management of the envelope, its budgets and budget lines. |
| Expense-consuming entity. Information that cannot be modified taken from the budget line. |
| Identification code of the lot defined in the project |
| Review number that is generated by the system according to this format: (REV-)(MONTH)(YEAR)(Order number). |
Close
Action icon
This button is used to access the envelope inquiry for the selected line in the grid.
This button is used to access the budget line inquiry for the selected line in the grid.
This button displays the detail by object (envelope, budgets and lines) for the requested revision in the event of a revision of "Multiple" type.
Close
In addition to the generic error messages, the following messages can appear during the entry :
You have not checked anything. Do you want to exit without performing any action?
After presentation of the objects coming from the selection, this message is displayed when clicking on [OK] without having carried out a selection. Answering "Yes" to this message brings you back to the menu, and answering "No" makes you stay in the selection screen, allowing you to approve a review request.
*
This message is displayed when the user tries to carry out an approval via their messaging service without being logged in with the signer code expected for the approval.
The review does no longer need to be approved
This message is displayed if the user tries to conduct an approval through their mailbox: the object has already been approved through the dedicated menu or through the linked file received by mail.
Mandatory field
This message is displayed when the approval is rejected without a reason having been entered for this rejection.
You have entered a budget revised amount larger than the envelope revised amount. Modify the budget revised amount or the envelope revised amount.
You have entered a budget line revised amount larger than the budget revised amount. Modify the budget line revised amount or the budget revised amount.
You have carried out a review decreasing the envelope amount, and the envelope available amount is now insufficient. Modify your entry, or first decrease the budget if such a review is possible.
You have carried out a review decreasing the budget amount, and the budget available amount is now insufficient. Modify your entry, or first decrease the budget lines if such a review is possible.
You have carried out a review decreasing the budget line amount, but the budget line contains expense entries that are larger than the modified budget line amount. Modify your entry.
You have entered a revised amount equal to the initial amount: this is not a review. Modify your entry or abort review.
When reviewing a budget by fiscal year, you have entered an amount "Taken from the envelope reserve" larger than the amount of this reserve. Selecting [OK] in this message brings the amount "Taken from the envelope reserve" up to the maximum amount for this reserve.
It is incorrect to distribute the increase between the reserve and the left to distribute from the higher level. The minimum amount to take from the reserve is displayed in the message and calculated according to the left to distribute, which in this case is insufficient for the entered reserve amount to be approved.
When reviewing a budget line, you have entered an amount "Taken from the budget reserve" larger than the amount of this reserve. Selecting [OK] in this message brings the amount "Taken from the envelope reserve" up to the maximum amount for this reserve.
You have tried to enter an amount in columns "Taken from reserve", "Taken from not distributed" or "Extension" before entering the amount of the requested review. Enter the amount of the requested review first.
This message is displayed when the distribution between the amount taken from the reserve and the amount taken from the left to distribute does not match the amount of the review requested. Check your entry and correct the distribution.