Field help (BOMOFS2) 

The reorder lead-time is used during launch and in the MRP calculation, in order to calculate the date of the component (material) requirement with respect to the subcontract start date of the parent.
It is expressed in calendar days. A negative value can be entered.

Examples:
Let us consider a subcontract order whose subcontract start date is on the 26/06.