It is possible via a contextual button to enter start and end times.
In that case, the system automatically calculates the actual operation time.
The operating time:
- in hours or minutes (see the time unit),
- is expressed for 1, 100, 1000 or a lot of units of the operation based on the management unit,
- can be proportional or fixed based based on the operating time type.
Example:
Time unit = Hours
Time type = proportional
Management unit = Time for 100
Operating time = 2
Operating unit = Kg
Finished product unit = Un
REL-OPE conversion coefficient = 0.5
The operation time is equal to 2 hours for 100 Kg. If the Work Order is launched for 1000 units of finished product, the time necessary to produce this operation is 10 hours to obtain 500 Kg.