This lead-time, expressed in calendar days, can only be entered if the product is of the category: Sub-contracted.
In a sub-contract operation without WO, the lead-times used to calculate the planned receipt date of the service are used in the following priority order:
- the lead time on the subcontract fee of the service associated to the supplier
- the service subcontract lead time in the selected subcontract BOM
- the subcontract lead time specified in the Product-supplier record of the Service
- - the purchase lead-time specified in the Product-site record of the Service
- the reorder lead time specified in the Product record of the Service.
If no lead time is associated to the service, the lead time of the subcontracted product is used, in the following priority order:
- the subcontract lead time specified in the Product-supplier record
- - the purchase lead time specified in the Product - Site record
- the reorder lead time specified in the Product record.