Filter for results within a range of 'labor' work centers. For a single work center, enter the same work center code in the from/start Labor center (Subcontract work center) and to/end Labor center fields.
The work center site of a 'labor' work center must match the site for the routing code, if defined.
Scheduling is not carried out for labor work centers as they are considered secondary and 'always available' (or available at the same time as the main work center). Their load is managed for information purposes only using the coefficients defined for the main work center.
If the main work center is of type 'subcontracting' there is no associated secondary work center.