This field identifies the end or required completion date for this work order. The date is determined by the Scheduling mode :
- 'Backward' scheduling respects this date. You must, therefore, define this date manually.
- 'Forward' scheduling respects the defined Start date. Leave this field blank. The system will calculate the date from the production lead time, reduction factor and economic quantity defined on the product-site record.