This field identifies the date this operation must be completed. The date is determined by the Scheduling mode and by the Scheduling status fields, as follows:
- If this work order is 'Not scheduled', this operation's end date matches the end date for this work order (as defined on the Headertab)
- If this work order is 'Scheduled', this operation's end date will be the latest date this operation can be completed according to the scheduling process. That is, this date will be determined by the sequence of operations in time according to the durations, slack times and relationships in the routing.