Example: Time unit = Hours Time type = proportional Management unit = Time for 100 Operation time = 2 Operation unit = Kg Finished product unit = A REL-OPE conversion coefficient = 0.5
The operation time is equal to 2 hours for 100 Kg. If the Work Order is launched for 1000 units of finished product, the time necessary to produce this operation is 10 hours to obtain 500 Kg.