Use this check box to define the replanning behavior when a resource is sufficient to cover the requirements:
- If the reduction is not authorized, replanning does not suggest modifying the resource quantity.
- If the reduction is authorized, replanning suggests reducing the resource quantity up to the requirement.
- If the reduction is not authorized, replanning does not suggest modifying the resource quantity.
- If the reduction is authorized:
- If the resource quantity is less than the batch/lot, replanning does not suggest modifying the resource quantity.
- If the resource quantity is greater than the batch/lot, replanning suggests the quantity is either the requirement or the economic lot, whichever is the greater value.