This entry point is called when the RELSTRDAT - ‘Level on WO start date change’ site parameter is set to Yes. This entry point is used to prohibit the leveling of work order materials when the work order start date is changed (directly or indirectly by modifying the end date).
There is no transaction in progress.
There is no open log file.
The [M:MFG0], [M:MFG1] and [M:MFG2] screen classes are loaded based on the [L]WMEMDAT value of the WO start date before modification.
The GPE variable is used. It is set to the value 0 by default.
It must be set to 1 in the specific processing in order to short-circuit the WO materials leveling based on the [M:MFG1]STRDAT value of the WO start date after modification.
In the table below, the Significant content flag indicates that the content matches the context.
Table | Significant content | Table title |
MFGHEAD | No | WO header |
MFGITM | No | Released products |
MFGOPE | No | Operations |
MFGMAT | No | Materials |
MFGPRN | No | Documents |
ORDERS | No | WIPs |
SCHEDULING | No | Scheduling |
OPERATIONS | No | Load WIP |
ROUTING | No | Routing header |
ROUOPE | No | Routing operations |
ROUSCD | No | Routing - Scheduling |
BOM | No | Bill of materials |
BOMD | No | BOM lines |
FACILITY | No | Site |
ITMMASTER | No | Product |
ITMFACILIT | No | Product-site |