Manufacturing > Analyses > Resource analysis report 

This function is used to display on paper or on the screen the results of the last production analysis started along the resource axis. It is based on the production tracking. It only considers the work orders having been submitted to a tracking over the specified period. It generates a result focused on the work center (main work center and labor work center)

It is used to directly print the results for the resource type analyses.

  • Use of the resources: Calculation oriented towards the planned time/achieved time
  • Yield of the resources: Calculation oriented towards the planned quantity/achieved quantity

This function is also used to relaunch a production analysis along the resource axis for a specific production site.

Prerequisite

SEEREFERTTO Refer to documentation Implementation

Screen management

Entry screen

Presentation

This function uses only one screen.

The purpose is to determine the main selection criteria for the report to be printed.

Selection criteria

Production site

This field is loaded by the production site associated with the operator. It is possible to select another site.

Analysis end date

The system searches for the print the analysis corresponding to the indicated end date. If the mentioned end date does not correspond to a completed analysis, the print will not give any result.

Selection of the analysis choice

The required analysis needs to be specified, only one choice is possible simultaneously.

New analysis

It is possible to carry out a new analysis by checking the "Update analysis" box and stipulating a start date for the analysis. This new analysis will take the place of the previous analysis having the same end date.

Start/End range

Information can be extracted from the analysis for a selection of work center groups or work centers for the selected site.

Close

 

Fields

The following fields are present on this tab :

Selection criteria

The production site associated with the user is proposed by default. It can be modified by another site authorized for the operator, depending on its authorizations.

  • Analysis end date (field MSTDAT)

Use this field to filter the orders to be loaded.

SEEWARNINGObserve loading times.

Analysis selection

  • Analysis to edit (field PROANA)

List of the production analysis oriented towards "products".


Block number 3

  • Refresh the analysis (field CLCANA)

Indicator for the analysis of production data.
If this indicator is not abled, the print bases on a previous analysis.
If this indicator is abled, a new analysis is carried out.


  • Analysis start date (field STRANA)

Start date for the production analysis period.


Start - end range

  • Work center group (field WCRDEB)

The work center group is a physical or fictitious entity grouping several work centers of machine, labor or sub-contracting type.

  • field WCRFIN

 

  • Work center (field WSTDEB)

The work center is attached to a work center group. It corresponds to a production resource on which a routing operation is carried out.

This is an entity for which it is requested to plan loads and track production times.

Each work center is associated with an attachment site.

  • field WSTFIN

 

Close

 

Error messages

In addition to the generic error messages, the following messages can appear during the entry :

Site name: Not a production site

This message appears when the specified site is not a production site

Mandatory field

This message appears when no information is entered in the site field.

Work center group (name of work center): Record does not exist

This message appears when the indicated work center group is wrong

Tables used

SEEREFERTTO Refer to documentation Implementation