Refer to documentation Implementation
This function is made up of 8 tabs. The first two present a global view of the production cost for the works order. The other tabs are used to analyze in greater detail each cost category.
Presentation
This tab presents the general information for the Works order (WO) :
The site
The WO number
The tracking type (WO, product or miscellaneous)
The adjustment pro rata
The quantities (Planned, Actual, Rejects and remaining)
The dates (Start, End, First tracking and last tracking)
It should be noted that all the tracking types load the WIPCOST and MFGWIP tables. In this latter, for the production tracking by WO, there will be a record by order. In the case of miscellaneous type tracking, there will be a record by work center and by period. Finally, for the product type tracking, there will be a record by routing and by period for the operations and a record by period for the material tracking.
Close
Fields
The following fields are present on this tab :
Block number 1
| Work order/sub-contract order numbers used to select a cost price. |
| The production site associated with the user is proposed by default. It can be modified by another site authorized for the operator, depending on its authorizations. |
|   |
  |
|   |
|   |
|   |
|   |
Quantities
|   |
|   |
|   |
|   |
Dates
|   |
|   |
|   |
|   |
Close
Presentation
This tab displays all the accumulations for each cost type :
Material
Labor
Machine
Subcontracting
Overheads
Totals
Balance : this line is entered when the WO is closed.
The "Actual cost" column displays what has been consumed for each cost type. The material costs are obtained by adding the actual value of the issue movement transactions. For the Subcontract cost, it is based on what has been invoiced and for the Labor and Machine, it is based on what has been calculated from the valuation dimensions.
The "Standard cost" column displays the detail of what has been entered to stock. This receipt to stock can be carried out at standard price, revised standard price or order price (provisional standard cost or provisional release cost) according to the valuation method. All these costs are detailed by material, labor, machine..... and this detail is then stored in the production reporting records in the WIPCOST table. Therefore in the "Standard cost" column the sum of all these movements can be found.
Once the production cost calculation is carried out, the value of the rejects that have been declared is displayed in this column.
The calculation of the cost of the rejects declared for an operation is based on the cost of the operation and the components that are attached to it.
For example:
Data for the example
Operations | ||||
No. | Unit | Qty | Rej Q | Amount |
5 | One | 20 | 1 | 400 |
10 | Kg | 3 | 0,5 | 300 |
Components | |||
Name | Oper | Qty | Amount |
A1 | 0 | 3 | 150 |
A2 | 5 | 4 | 250 |
Intermediate grid
Oper no. | %reject | Amount | Amnt A1 | Amnt A2 |
5 | 5% | 400,00 € | 75 € | 250,00 € |
10 | 16,6% | 300,00 € | 75 € | - € |
The amount for component A1, which is not attached to an operation, is distributed across all of them.
Oper no. | Oper rej amnt | Reject A1 | Reject A2 | Total |
5 | 20,00 € | 3,75 € | 12,50 € | 36,25 € |
10 | 113,33 € | 24,38 € | 39,58 € | 177,29 € |
The operation reject amount for operation 5 is 20: 5% * 400
The operation reject amount for operation 10 is 136: 16,6% * (400 + 300 - 20)
The A1 reject amount on operation 5 is 3.75: 5% * 75
The A1 reject amount on operation 10 is 24.38: 16,6% * (75+75 - 3,75)
The A2 reject amount on operation 5 is 12.5: 5% * 250
The A2 reject amount on operation 10 is 39.58: 16,6 * (250 - 12,5)
The differences found between planned and actual are found in the "Variance" column.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Presentation
The Totals (acctg) tab contains the same lines and columns as the Accumulations tab. It presents the values that have been transferred to accounting for each cost type.
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
Presentation
This tab presents the costs that have been declared in production. There is a line for each released product (that has been the object of a tracking record). For each of these there is:
The completed quantity
The actual amount as well as that transferred to accounting
The actual overheads as well as those transferred to accounting
The adjustment value
A right click on the line provides access to the "Product cost detail". This screen presents similar information but by detailing each tracking report. From this there is the possibility to zoom to the original tracking record or the accounting document that has been generated.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Action icon
Presentation
This tab displays the costs from the material tracking. There is a line by component (that has been the object of a tracking record). For each of these there is:
The completed quantity
The actual amount as well as that transferred to accounting
The actual overheads as well as those transferred to accounting
A right click on the line provides access to the "Material cost detail". This screen presents similar information but by detailing each tracking report. From this there is the possibility to zoom to the original tracking record or the accounting document that has been generated.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Action icon
Presentation
This tab presents the costs for the labor reporting. There is a line by operation (that has been the object of a tracking record). For each of them there is:
The completed quantity
The actual set-up and operation times
The actual amount as well as that transferred to accounting
The actual overheads as well as those transferred to accounting
Aright click on the line provides access to the "Labor cost detail". This screen presents similar information but by detailing each tracking report. From this there is the possibility to zoom to the original tracking record or the accounting document that has been generated.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Action icon
Presentation
This tab presents the machine tracking costs. There is a line by operation (that has been the object of a tracking record). For each of them there is:
The completed quantity
The actual set-up and operation times
The actual amount as well as that transferred to accounting
The actual overheads as well as those transferred to accounting
A right click on the line there provides access to the "Machine cost detail". This screen presents similar information but by detailing each tracking report. From this there is the possibility to zoom to the original tracking record or the accounting document that has been generated.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Action icon
Presentation
This tab presents the subcontract tracking costs. There is a line by operation (that has been the object of a tracking record). For each of them there is:
The actual quantity and the reject quantity
The actual set-up and operation times
The actual amount as well as that transferred to accounting
The actual overhead costs
A right click on the line provides access to the "Subcontract costs". This screen presents similar information but by detailing each tracking report. From this there is the possibility to zoom to the original tracking record or the accounting document that has been generated.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Action icon
Presentation
This tab displays a summary of the overhead costs by nature. For each of theses there will be:
The material costs
The labor costs
The machine costs
The subcontract costs
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close