This lead time is loaded, in order of priority, as follows:
- the lead time on the subcontract fee of the service associated to the supplier
- the service subcontract lead time in the selected subcontract BOM
- the subcontract lead time specified in the Product-supplier record of the Service
- - the purchase lead-time specified in the Product-site record of the Service
- the reorder lead time specified in the Product record of the Service.
If no lead time is associated to the service, the lead time of the subcontracted product is used, in the following priority order:
- the subcontract lead time specified in the Product-supplier record
- - the purchase lead time specified in the Product - Site record
- the reorder lead time specified in the Product record.
This field is managed depending on the setup of the entry transaction of the subcontract order.