Field help (OPESTR) 

The subcontract operation start date is determined by default as follows:
End date - Lead time.
The end date is updated when it is modified. If the calculated end date is later than the receipt date of the released product, the latter is modified.

This field is managed depending on the setup of the entry transaction of the subcontract order.