Projects > Time management > Time approval > Time approval - Implementation 

Prerequisites

Activity codes

The following activity codes (sorted by type) may have an impact on the way the function operates :

Dependent activity codes

These codes are never entered in folder management, because their value is calculated :

 PJMSA (PJM & Sales modules enabled).

Functional

 PJM : Project management

Sizing

 ANA : No. of analytical dimensions

 PJMTI : Time entry

General parameters

The following general parameters may change the way the function is working :

Common Data

 PJMTIMENT (defined at level Site) : Time entry control phase

Authorizations

An authorization can be granted for this function to limit the processes to a company or a site.

The following options can be activated or deactivated for each user :

 Validate

 Control

 Approve

 Reject

Tables used

No table is used by this function.