Arrival date or expected arrival date + transport lead time from the transport arrival place to the receiving site of the order line + release time on the receipt site (place).
Since no transport mode or carrier is specified on the shipment line of the order line for carrying the goods from the arrival place to the receipt site, the considered lead time is the one set up without carrier and with a Not defined transport mode. If this setup is not available, the calculation of the planned receipt date is performed with no transport lead time.
If the information required for the calculation is not provided, the date is initialized based on the planned receipt date of the order.
This date can be modified as long as the shipment status is Created. Any modification to this date at the level of the Shipment function is automatically applied at the level of the Pre-receipt screen, and vice-versa. The date is also updated in the ORDERS table used in the MRP calculation. However, it is not updated in the order.