Field help (NCSPLANNER) 

Use this field to identify the Planner (project manager) who will be responsible for planning the set of 'global actions' that will form the corrective and preventive Action plan for this incidence of non-conformance. They will be responsible for planning the approach to be taken to eliminate the problem. They will also be responsible for controlling or managing the corrective or preventive actions, using their Action plan, through to a successful correction and approval of a product that is 'fit for purpose'.

The default planner is the user defined in parameter NCSPLADEF - Default planner (chapter TC, group NCS). You can assign this non-conformance incident to a different planner, if required. Type in, or select a user code from the list of users approved for involvement in your Non-conformance management process as 'planners'.

 You can only change the default or the assigned planner if you meet one of the following conditions:

  • You are the current QA manager or Planner for this non-conformance incident;
  • The new planner's User recordhas approval for thesite specified on this non-conformance incident;
  • This non-conformance incident is currently active, that is, it is not at status 'Closed'.