This function is used to define prototype plannings for the resources of the current folder.

A prototype planning is defined by a code and for a given year. It is characterized by the scheduling of prototype weeks for each week of the year considered.

SEEINFO it is possible to define several prototype plannings for the same year. Each planning is identified by a single code.

Prerequisites

SEEREFERTTO Refer to documentation Implementation

Screen management

This function contains a grid with weeks to fill.

Entry screen

Presentation

The operating principle is to define a prototype week for each week of the year considered.

A prototype week may not be associated to a week of the year considered. In that case, this week will be considered as "Undefined" and will not be considered when the resource's individual planning is initialized.

SEEINFO the prototype week can be initialized on all the lines in the grid. The principle is then to copy the prototype week from one line to the others. For that purpose, the user should go to the prototype week on a line and by right-click choose the option "Copy to the next lines"

Close

 

Fields

The following fields are present on this tab :

Block number 1

  • Year (field YEA)

 

  • Code (field COD)

Specifies the planning code.

  • Description (field TPYDESAXX)

 

  • Short description (field TPYSHOAXX)

 

Grid

  • Start date (field WEESTR)

 

  • End date (field WEEEND)

 

Specifies the prototype week code.

Close

 

Error messages

The only error messages are the generic ones.

Tables used