Refer to documentation Implementation
The Recalculate work order FDMA function displays two selection screens:
A log file displays the results of the run.
Presentation
Type in, or select the site at which the work orders are to be refreshed, then select the work orders statuses to be included in the run.
A number of ranges are displayed.
You can optionally select the work orders by applying a calculation formula.
Close
Fields
The following fields are present on this tab :
Selection criteria
| The production site from which the work orders are to be selected. The production site defined on the user record is displayed by default but can be amended. |
| Enter, select or build an Enterprise Management filter calculation expression using the formula editor.
|
Status
| Filter for results within a range of work order statuses. Selection respects the lowest stage to the selected stage of the work order in the production cycle, as follows: For work orders incl. (including) status <Being optimized>. All work orders that have been submitted to Production Scheduler for scheduling but have not yet been included in a "published plan". For work orders incl. status <Optimized>. All work orders submitted to Production Scheduler that are currently being optimized for scheduling or have been included in a "published plan" but production has not yet started. For work orders incl. status <In progress>. All work orders submitted to Production Scheduler for scheduling. This includes all work orders that are currently being optimized for scheduling and those that have been included in a "published plan", whether production has started or not. The work order status values are defined in local menu 339 - Work Order Situation. |
Work order
| Filter for results within a range of work orders. For a single work order, enter the same work order in the from/start Work order no. (Work order number) and to/end Work order no. fields. |
| Filter for results within a range of finished products (BOMs). For a single bill of materials (BOM), enter the same product code in the from/start Released product and to/end Released product fields. |
| Filter for results within a range of dates. For a single day, enter the same date in the Start date and End date fields. You can leave the Start date field blank to search all records to date. |
|   |
| Filter for results within a range of project codes. For a single project, enter the same project code in the From/start project and To/end project fields. If the value of this field includes a character such as an exclamation mark "!" this field links to the structure of the project. The character is the separator between a project code and the structure, either the project budget structure or the project operational (task) structure. For example, if a material task code is "USA-P3" and a project code is "USA12345678", this field displays a link to the project operational structure as "USA12345678!USA-P3".
|
WOs using material/component
| Enter or select a component code to filter for work orders containing this component. |
| This field indicates which version of this component (material) applies. Major versions might be used where there have been increased or significant changes to the original or previous version, that is the "form, fit or function" has changed. This field is not populated if the component code defined in the Component or Material field is not version managed. |
| Filter for results within a component requirement date range. For a single day, enter the same date in the from/start Material requirement and to/end Material requirement fields. You can leave the start Material requirement field blank to search all records to date. |
Close
Presentation
You use this tab to confirm the details of the work orders to be refreshed.
To exclude a specific work order, either leave the check box clear or click Delete from the Actions icon.
A log file displays the results of the run.
Fields
The following fields are present on this tab :
Block number 1
| The production site from which the work orders are to be processed. |
| Select this check box to select this line. |
| This field displays the work order number. |
| This field indicates the status of the work order. This status can be Pending, Being optimized or In progress. |
| This field indicates the current stage of this work order in the scheduling process. This status can be Scheduled or Optimized. |
| This product code describes what is referred to as a "Bill of Materials" or a "BOM". A BOM contains structured information for making and costing a product. It defines the components that make up a product, and given this, the cost of the product. The BOM code matches the product code. |
| This field identifies the planned or actual production start date of the work order. |
| This field identifies the end or required completion date for this work order. |
Action icon
Click Include all to select all displayed work orders. |