Reports > Module Manufacturing > Report RENDRESS (Resource yield) 

This report describes the results of the production anayses for the resource dimension view and more particularly the resource yield (main work center and labor work center).

(see the Production analyses and Product analysis printing documentations)

This report presents by bite and by work center the sum of quantities (planned and actual) and the reject reported at the level of each work center, an indication of the average yield and the average reject.

The results are totalled at the level of each work center.

The display presents:

  • the sum of the planned quantities on the defined period,
  • the sum of the actual quantities on the defined period,

The sum of the rejects represents the reject quantity reported at operation tracking level

The system submits the average yield and the average reject, and it stipulates the number of operations achieved on the work center.

Prerequisite

List of criteria

Parameter

Parameter title

Type

wcrfcydeb

Plant range

FCY

wcrdeb

Work center group range

WCR

wstdeb

Work center range

WST

enddat

Analysis end date

D

impselections

Print selections (Local menu No, Yes)

M1

Description of the report

 Explanation of the formulas being used

Average yield=(Sum achieved/sum planned) *100

Average reject=(Reject/sum planned) *100

Example of a calculation

Let us consider the following elements on the CH1 work center

On the analysis period, the nominal capacity of CH1 is 95 hours.

 

WO1

WO2

WO3

Planned set-up time (hours)

2

5

3

Operating time (hours)

12

35

23

Planned parts

125

250

310

(fixed time)

Total planned quantity: 685 pieces

Production data

 

WO1

WO2

WO3

Correct achieved parts

110

245

305

Rejected parts

5

6

4

Achieved parts

115

252

309

 

Actual quantity: 115 + 252 + 309 = 676

Rejected quantity: 5 + 6 + 4 = 16

Correct achieved quantity: 110 + 245 + 305 = 660

Average yield: (660/685)*100 = 96,35 %

Average reject: (16/685) = 2,33 %