Refer to documentation Implementation
The DO is selected, then the quantity to be deferred is specified for each DO line.
Presentation
For each DO line, the following information is displayed:
Preparedquantity: prepared CU quantity, validated upon PO validation.
Shippedquantity: previously shipped CU quantity.
Deletedquantity: CU quantity deleted by the DO Cancellation function
Deferred quantity: CU quantity to be reintegrated or deferred. The entered quantity must be smaller than the quantity to be shipped. Corresponds to the quantity to be shipped minus the quantity "pending transfer".
When part of the DO line has been deferred, it is necessary to reintegrate it upon its shipment.
The "Deferred" column indicates the deferred quantity for each line if it is entered, or it enables the quantity to be deferred to be entered.
Quantity to be shipped: quantity to be shipped during the next shipment. The field is updated based on the entry of the quantity to be deferred.
The deferred quantity or quantity to be reintegrated remains modifiable at any time as long as the DO has not been shipped.
Quantity pending transfer:quantity in CUs of a DO "pending transfer", in other words, a DO shipped to another site. These goods cannot be deferred as long as they are "pending transfer". If the partial deferment of a DO has been performed before shipment confirmation of the "inter-site" round, said partial deferment cannot be removed as long as the DO is "pending transfer".
Report
Step 1: Enter the quantities to be deferred on the lines to be deferred
Step 2: validate the action using the "Save" button.
Only those lines with a normal or Kit nature can be entered.When entering a kit, the component lines attached to it are selected by default.
Process: The output movements are then updated and split in case of partial line deferment. The status of the deferred movements moves to status 7- Deferred upon shipment.
A print-out is automatically generated to indicate the deferred DO lines and quantities.
The DO can then be shipped and the movements taken into account in the shipment will be the movements that are not deferred.
ReintégrationStep 1: Enter the quantity to be reintegrated to ship it
Step 2: validate the action using the "Save" button.
If a partial shipment has already taken place, the shipped quantity is already entered, and the quantity to be shipped is null.
If it has not taken place, the quantity to be shipped remains to be entered.
Process: The corresponding movements move from Status 7-Deferred upon shipment to status 8-Validated (initial status)
A print-out is automatically generated to indicate the deferred DO lines and quantities.
Close
Fields
The following fields are present on this tab :
Delivery order
| Numerical sequence automatically assigned by the system upon validation of the DO header. This number features an information specific to the system, all depositors included. This piece of information features a unique access key to a Delivery Order. |
|   |
|   |
|   |
|   |
|   |
Grid DO lines
|   |
|   |
|   |
|   |
|   |
| Quantity express in CUs to be deferred or reintegrated. |
|   |
| Mentions the quantities in CUs "pending transfer". These quantities are said to be "pending transfer" as soon as the "inter-site" round to which the DO is assigned has been confirmed. Once the round has been confirmed, the deferment or cancellation is not longer possible. |
Close
Action icon
By default, the following reports are associated with this function :
REPORTEXP : Postponed shipment
This can be changed using a different setup.
In addition to the generic error messages, the following messages can appear during the entry :
Partial delivery prohibited.
The DO header set-up does not allow the DO to be shipped in a split fashion.
"Deferred" field error. Maximum quantity XX CUs
The 'deferred' quantity must not be larger than the quantity 'to be shipped' minus the quantity 'pending transfer'.