Refer to documentation Implementation
The WIP (Work in Progress) stock inquiry contains a header information section for your selection criteria and a single tab for the results.
Presentation
You use the header information to define the site, the range of products for which you want to view the projected stock movements and the sort order.
Close
Fields
The following fields are present on this tab :
Block number 1
| Enter or select the storage site where the selected product is active. The Selection icon (magnifying glass) only suggests products that are referenced in the products-sites table. |
Block number 2
| Enter the selection start product number. The product ranges limit the report to these products only. |
| Enter the ending product number for the selection. Product ranges are used to restrict the report to these products only. |
| Select the classification criteria for the display of the returned lines. |
Close
Presentation
This tab displays all orders in process for the selected order types. The status of each order is included.
Close
Fields
The following fields are present on this tab :
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
|   |
Close
Action icon
Click Significance from the Actions icon to view the meaning of the acronyms used to describe the different types of in-process orders. For example, WOF means Work Order Firm, WOP means Work Order Planned, WOS means Work Order Suggested and MWF Material Requirements Firm.
Click Load in progress from the Actions icon to view the source load.
Click Customer order from the Actions icon to view the source sales order.
Click Work order from the Actions icon to view the source work order.
Close
The following fields are included on the window opened through this button : Start - end range
Selections
Suggestion filter
Block number 3
Display
Close Click the Criteria action to access additional selection criteria. Entry type. Use the Entry type and Entry range fields to select the orders that should be taken into account in the projected calculations. Filters by order status. Use these check boxes to select the status (firm, planned, suggested) of the orders that should be taken into account in the projected calculations. Filters on suggestions. Use these radio buttons to specify whether to display MPS suggestions and/or MRP suggestions in the projected stock calculations. By default, all suggestions are displayed. Apply the loss percentage. Select (tick) if the work orders in process remaining quantities must be reduced by the product-site loss percentage. Screen code. You can select the required customized inquiry screen, if you are using personalized inquiries. Please see the Inquiry screens documentation. You can save one or several sets of criteria using the Memoaction. You can recall these using the Recallaction or delete them using the Delete memo action. |
This graph presents the maximum stock, the safety stock, resources, requirements and the evolution of the in-process stock over time.
You can modify the reference date, frequency and number of periods. Click the Search action to display the results.
This graph displays the resources and requirements by period.
You can modify the reference date, frequency and number of periods. Click the Search action to display the results.