Refer to documentation Implementation
The Simulated standard costs function contains a home section in which you define the control parameters for a specific product, and 3 additional sections:
You can choose to display the calculated costs results in a table, or as a pie chart.
Presentation
You use this section to load the simulated costs for a specified reference date, for a specific product, and site.
Close
Fields
The following fields are present on this tab :
Block number 1
| Enter or select the product code to inquire upon. |
| Enter or select the storage site where the selected product is active. The Selection icon (magnifying glass) only suggests products that are referenced in the products-sites table. |
| Use this field to indicate which major version of this product applies. Major versions might be used where there have been increased or significant changes to the original or previous version, that is the 'form, fit or function' has changed. Type in, or select a version code from the list of version codes displayed. This field is not available for entry if the product code defined in the Product field is not version managed. |
| Use this field to indicate which minor version of this product applies. Minor versions might be used where there have been minor features or changes in functionality, or significant fixes applied to a specific major version. Type in, or select a version code from the list of version codes displayed. This field is not available for entry if the product code defined in the Product field is not version managed. |
| Type in the date for which the costs for this product at this site, and validity period, are to be loaded. |
| Use this field to define the start date of the validity period for this cost. |
| Use this field to define the end date of the validity period for this cost. |
| This field displays the product category to which this product is assigned. You cannot amend this field. |
| This field displays the cost group set on the product. It can be amended. Cost calculations are used to break down material costs. Use this field to define where (subtotal) the material cost for this product category must be posted.
|
| This field displays the method that will be applied when the cost calculations are performed.
|
| This field displays a warning if this particular product-storage site record already has a revised / simulated standard cost assigned to it for the defined validity period. You will not be able to update the revised / simulated standard cost. |
Block number 2
| You can include overheads in the cost calculations. To include overheads for a specific stock movement type select the required movement type. |
| Select an overhead code. Overhead codes are used as follows:
The overheads column that contains the formula or fixed rate to be used in the cost price calculation functions is defined by parameters. For standard cost calculations the OVECOLSTD - Standard calc overhead column parameter (GPA chapter, COS group) applies. You can modify the column to be applied before running the calculation. |
| Use this field to select the calculation type.
|
Close
Presentation
Use this section to enter costs for this level of the bill of materials (BOM), for this product-site combination.
You can choose to display the calculated costs results in a table, or as a pie chart. Click Show list/Show graph, as required.
Close
Fields
The following fields are present on this tab :
Level cost
| Use this field to enter the current stock value for this product. |
Code of the currency in which the customer costs are expressed. |
| Use this field to enter the current stock value for the components directly associated with the top level of the bill of materials (BOM). |
| Use this field to enter the machine cost for this product-site combination. |
| Use this field to enter the labor cost for this product-site combination. |
| Use this field to enter the subcontracted cost for this product-site combination. |
| Use this field to enter the overhead costs for this product-site combination. |
| This field displays the total costs for this product-site combination. |
| Use this field to define the quantity for the basis of the calculations. |
This field displays the unit of the calculation quantity. |
| Click this Search icon to view the material, machine, labor and overheads cost breakdown. |
| This field displays the description of the calculated cost. |
| This field displays the result of the calculated cost. |
Close
Presentation
This section displays the total value of the simulated cost for this product-site combination, for the complete bill of materials (BOM). The figures in this section are fixed values.
You can choose to display the calculated costs results in a table, or as a pie chart. Click Show list/Show graph, as required.
Fields
The following fields are present on this tab :
Multilevel totals
| This field displays the total stock value of the components in this product design BOM revision. You can amend this figure as required. |
Code of the currency in which the customer costs are expressed. |
| This field displays the total machine cost of the components in this product design BOM revision. You can modify this figure as required. |
| This field displays the total labor cost of the components in this product design BOM revision. You can modify this figure as required. |
| This field displays the subcontract service cost. The price used to value the service is specified by the VLTSCEOEXT - Service value price/planned PC parameter (ACH chapter, COS group). |
| This field displays the total overhead costs of the components in this product design BOM revision. You can modify this figure as required. |
| This field displays the total value of stock in hand for this product-site combination in the complete bill of materials (BOM). |
| This field displays the quantity included in the calculations. The default quantity is the Economic order quantity (field EOQ (REOMINQTY)) defined on the product-site record or the Technical lot (field MFGLOTQTY) defined on the product-site record, or 1. |
This field displays the unit of the calculation quantity. |
| Click this Search icon to view the material, machine, labor and overheads cost breakdown. |
| This field displays the description of the calculated cost. |
| This field displays the result of the calculated cost. |
Presentation
This section displays the calculation parameters applied when this product was last calculated by the Simulated cost calculation run (CALCSTSIM):
You can recalculate the simulated cost by selecting the Recalculate icon.
You can print the results of the run from this function. A log file detailing the results of the run is also produced. The end of run reports are in summary if the Multilevel field is set to No.
Close
Fields
The following fields are present on this tab :
| Multiple routings can be defined for a single product. Each routing code can be assigned specific management features. These include restriction of the routing to a specific site and to specific areas of functionality (for use in a manufacturing environment, for costing or for capacity planning). This field defines the route used for the calculation of the components, machines, resources, workforce and subcontractors. From this routing code, the program searched for the first valid alternative bill of materials (BOM) for the defined site. If this field is blank, only a material calculation was made (valuation and calculation of material overheads). |
| Multiple bills of materials (BOMs) can be defined for a single product. Each BOM code can be assigned specific management features. For manufactured or subcontracted products this includes restriction of the BOM to a specific site and to specific areas of functionality (for costing or for capacity planning). |
| This field displays Manufacturing if you manufacture this bill of materials (BOM); if it is procured from a subcontractor, it displays Subcontracting. |
| This field defines the type of cost used to value materials. The possible values are:
|
| This field displays the dimension rate used to value time. |
| This field defines how the fixed overhead costs (material loss, setup rate, operation loss rate, fixed rate) were distributed.
|
| This field defines how overheads were valued. The value of an overhead was calculated by applying the fixed rate or the formula in the chosen calculation column. |
| This field is only active for a single product calculation.
|
| Click this Recalculate icon to recalculate the standard cost for this product-site combination. |
Close
By default, the following reports are associated with this function :
ITMCOST : Detail cost calculations
NA-ITMCOST : Single Level BOM Report
This can be changed using a different setup.
Click the History action to view the current and past standard cost records for this product-site combination. |
Click the Copy action to copy the costs. You can copy the costs to a different site, or create a new type of cost from these figures such as a new budgeted cost. |
Click the Calculation action to run the simulated cost calculations for the current costs displayed. |
Use this menu to enter the analytical dimensions for the movement that is created if the product is valued using the simulated cost valuation method.
Parameters from the STJVAL - Change of Costdefault dimension are used to load the sections for this movement.