Refer to documentation Implementation
Fields
The following fields are present on this tab :
| The standard operation is a "template" operation used to create or modify the routing operations. Recover the standard operation data:
When modifying a standard operation, the modifications are not passed on to the associated operations. |
| It is mandatory to enter a site for a standard operation. The chosen site conditions the choice of the work centers on which this operation is defined. These work centers must exist at the site in question. It is possible to define the same standard operation code on two different sites. |
|   |
Close
Presentation
This tab is used to describe the work centers of the operation, along with the running times. The times of the standard operation are entered in a time unit chosen in hours or in minutes, and for a given stock (or production) unit.
Close
Fields
The following fields are present on this tab :
Resources
|   |
| The principal work center corresponds to the production resource on which the routing operation will be performed. It can be of machine, labor or sub-contracting type. |
|   |
| The number of work centers makes it possible to manage the number of resources for identical resources in order to carry out an operation. For instance, a labor work center may comprise 3 people. This is indicated by entering 3 in the number of resources. |
|   |
| A labor work center can be associated with the machine-type or labor-type main work center. The labor work center times are calculated using two coefficients:
When creating a routing operation, the site attached to the work center must be the same as the site dedicated to the routing code, provided that the latter site is mentioned. This resource is considered as secondary and always available (or available at the same time as the main work center). Its load is managed for information purposes via coefficients applied to the main work center times. If the main work center is of sub-contracting type, no secondary work center can be associated. |
|   |
| The number of work centers makes it possible to manage the number of resources for identical resources in order to carry out an operation. For instance, a labor work center may comprise 3 people. This is indicated by entering 3 in the number of resources. |
Charged time
| The time unit defines how time for the operations in this routing is expressed. The time unit can be 'hours' or 'minutes'. It applies to the setup time, run time and the rate for all operations in the routing. |
| The operation time type conditions the production time entry.
|
| The setting time is a fixed amount of time necessary to prepare the work center. It is part of the work center load. It is expressed in the time unit specified:
|
|   |
| Depending on the resource being used, the number of decimals of the operation time can be insufficient to express the production time. |
| The basis quantity entry depends on the management unit. |
| The operation time is the time necessary to manufacture the product described in the routing. The operating time unit can be:
|
|   |
| The rate is a number of units produced by minute or by hour according to the time unit specified in the routing header (for an operation), or in the standard operation itself. |
|   |
|   |
| Efficiency is a way to measure compliance to the preset standards. It can be calculated over a given period by work center: Standard hours calculated for a given production divided by the actual hours worked. Two efficiency rates are managed depending on the following:
If both factors are entered, they add up. The WSTEFFINH - Work center efficiency history parameter (GPA chapter, MIS group) is used to specify whether the efficiency defined at work center level should be used on the routing operation.
|
| This percentage is used to balance the quantities on the production operations based on the released quantity. It is possible to introduce a shrinkage percentage on the work center, which is used to weight the planned runtimes for an operation using this work center by a loss or gain on the quantity produced for the work center. |
Labor factor
| This is the planned setting time to obtain the setting time allocated to the labor work center linked to the main work center. This coefficient applied to the planned setting time to obtain the setting time allocated to the labor work center linked to the main work center. |
| This is the coefficient applied to the planned operation time. It is used to obtain the operation time for the labor work center linked to the principal work center. This field is only available for entry if the labor work center is defined. Operation times are subdivided as follows: Proportional times are expressed for the production of an operation unit (and not in the stock unit of the finished product using the routing). |
Off time charge
| Preparation time is 'waiting time' set at the start of an operation. Preparation time is always expressed in hours. It does not use the time unit defined in the routing header (field Time unit). Preparation time is not applied to the work center load. Although preparation time is waiting time it can be used for the time it takes to prepare for an operation on a work center. This might be time for settling liquids or cleaning a machine. For this type of scenario, that is when preparation time is used for setting time at the start of an operation, the resource must be available. When scheduling preparation time the calendar for the defined resource is applied. This means that if, for example, a work center (machine or labor) runs from 08:00-12:00 and 13:00-17:00 with a break for one hour between 12:00-13:00, preparation time will be interrupted by the one hour break. If the operation requires an 'emergency release', a reduction coefficient can be assigned that makes it possible to completely remove any preparation time. |
|   |
| Waiting time is 'delay time' that occurs after an operation. It is non-productive time such as drying time or cooling time that occurs after a process has been completed on a machine and until the machine can next be used. Waiting time is always expressed in hours. It does not use the time unit defined in the routing header (field Time unit). Waiting time is not applied to the work center load. If machine time is required for an operation during the allowed waiting time you should add a new operation to this routing. A machine might be required for example, for drying or cooling components at a work center. The additional operation must be for the appropriate resource type, such as 'cooler'. When scheduling time for these resources if, for example, a work center (machine or labor) runs from 08:00-12:00 and 13:00-17:00 with a break for one hour between 12:00-13:00:
|
|   |
| Post operation, or post run time is a 'deadline' that occurs after waiting time. It is non-productive time, typically 'transfer time', or a transition period from one work center to the next work center that occurs after a process has been completed on a machine and until the machine can next be used. Waiting time is always expressed in hours. It does not use the time unit defined in the routing header (field Time unit). Waiting time is not applied to the work center load. If operator time is required for an operation during the allowed post run time you should add a new operation to this routing. An operator might be required for example, for the transportation or carriage, or the transition between two work centers. The additional operation must be for the appropriate resource type, such as 'carrier'. When scheduling time for these resources if, for example, a work center (machine or labor) runs from 08:00-12:00 and 13:00-17:00 with a break for one hour between 12:00-13:00:
If the operation requires an 'emergency release', a reduction coefficient can be assigned that makes it possible to completely remove any post run time. When scheduling time for these resources, if both waiting time and post run (post operation) time has been declared for the operation only the largest of the two values is used. |
|   |
Unit
| Work order operation quantities are expressed in the operation unit. Use this operation unit to express operating time in a different unit to that of the product being produced by the routing. For example, a product managed by unit is subject to three different operations, none of which produce intermediate stock:
There is no need to create semi-finished products for each production phase. The operation unit is associated with a conversion coefficient for the stock unit of the product being produced by the routing and the operation unit. |
Close
Presentation
This tab regroups technical information (tooling, workbench, image) and the information concerning the potential sub-contracting of the operation.
Those elements necessary to define the sub-contracting, either temporary or structural, are the sub-contracting product and the work center. It is also possible to specify the preferred supplier to which the sub-contracting order will be entrusted along with a reference price.
Note: The supplier can be modified on the routing, then on the WO. Furthermore it is always possible, when entering the order, to choose another supplier than the one proposed on the WO operation.
Fields
The following fields are present on this tab :
Description
| The technical sheet is used to record two types of information.
|
| This field is not associated with any application processing: it can be entered as information. |
|   |
Miscellaneous
| The tool is represented by a product reference whose category is of tool type. |
| This field is not associated with any application processing: it can be entered as information. |
|   |
Subcontract
| The sub-contracting code is used to determine whether the operation is carried out internally or if it is sent outside to a sub-contracting supplier.
|
| This is the code for a product with the category type ‘service’. |
|   |
|   |
| A subcontract work center can be used for the following:
A subcontract work center has the work center type set to 'Subcontracting'. Routing operations are validated to ensure the work center site of a 'subcontract' work center matches the site for the routing code, if defined. |
|   |
|   |
|   |
| In the case of the definition of a generic sub-contracting service, a reference price can be entered in the operation. |
  |
Fields
The following fields are present on this tab :
Detailed scheduling
| Operation grouping code. |
| Formula used to intervene in the formatting of the grouping code during release. |
Close
By default, the following reports are associated with this function :
ROUOPESTD : Standard operations listing
This can be changed using a different setup.
In addition to the generic error messages, the following messages can appear during the entry :
When a labour work center is entered in an operation, it must be different from the principal work center.
In the labor work center: the type of the labor work center MUST be labor.
In the sub-contract work center: the sub-contract work center must be of sub-contract type.
When there is a change to the units, this warning is used to stress the importance of coherence with the times already entered.
If the time is to be expressed by lot, it is necessary to enter the operation unit in order to specify that the time indicated is for a given quantity, expressed in this unit.
If the user has chosen to express the time by lot, it is necessary to enter the base quantity in order to specify that the time specified is for this quantity expressed in the operation unit.
A sub-contract code with the value "structural" signifies that the operation processed is always a sub-contract operation. Also, it is mandatory that the principal work center is of sub-contracting type.
This message appears if a modification has been requested for the sub-contracting code in such a way that this code has switched to the values "structural" or "temporary" and that the sub-contracting product is not entered.