General parameters > Chapter Common Data > Parameter ESTREVINIT (Estimated revenue init.) 

This parameter is used when calculating the estimated revenue for a project automatically.

ESTREVMET - Revenue estimation method parameter (TC chapter, PJM group). You use this parameter to define if the estimated revenue for a project can be calculated automatically.


The total estimated revenue for a project can be entered manually, or calculated automatically by clicking a Refresh icon in the project.

When clicked, the Refresh icon "requests" a value for the Estimated revenue at completion (EREVCOM) field in the project. However, before this value can be calculated the Estimated revenue at completion field must be initialized. You use this parameter to define the SQL query that is to be executed to initialize the Estimated revenue at completion field when the project revenue value is calculated.

The SQL query PJMREV is provided with your Sage X3 system to calculate the estimated revenue at completion from sales orders linked to the project. PJMREV is defined as the default value for this parameter but can be changed.

Level of localization/Global variable

This parameter is defined at the level Site.It belongs to Chapter TC (Common Data) and the Group PJM (Project management),The following parameters are also associated with this chapter and group :

Its values are defined by the function SQL query tool.

No global variable is associated with it.

Activity codes

The following activity codes (sorted by type) are associated with the parameter :

 PJM : Project management

Comments

The estimated total revenue amount is calculated and displayed in the project accounting currency. The associated currency is displayed in the Accounting currency field (EREVCUR).