This parameter is used when calculating the estimated progress of a project task automatically.
ESTPRTMET - Task progress estimation method parameter (TC chapter, PJM group). You use this parameter to define if the estimated progress of a project task is entered as a percentage manually, or calculated automatically.
The estimated progress of a project task can be calculated automatically on demand by clicking a Refresh icon in the operational structure.
When clicked, the Refresh icon "requests" a value for the Estimated progress (%) (PRCCPL) field. However, before this value can be calculated the Estimated progress (%) field must be initialized. You use this parameter to define the SQL query that is to be executed to initialize the Estimated progress (%) field when the project task progress percentage is refreshed.
The SQL queryPJMPRGT is provided with your Sage X3 system.PJMPRGT calculates progress by comparing consumed load against planned load for the labor task operations.PJMPRGT is defined as the default value for this parameter but can be changed, enabling your organization to customize the rules for the task progress calculation as required.
This parameter is defined at the level Site.It belongs to Chapter TC (Common Data) and the Group PJM (Project management),The following parameters are also associated with this chapter and group :
Its values are defined by the function SQL query tool.
No global variable is associated with it.
The following functions are associated with this parameter :
Projects > Projects > Project management
Projects > Projects > Snapshots > Financial snapshots
Projects > Projects > Utilities > Financial status extraction
Projects > Projects > Utilities > Financial snapshot extraction
The following activity codes (sorted by type) are associated with the parameter :
PJM : Project management